Cloud Egress Fees In 2027
Egress fees are what a cloud vendor bills when data leaves its network. On Amazon Web Services the list rate for internet transfer out starts near $0.09 per gigabyte after a free monthly allowance, so exporting 50 terabytes costs roughly $4,300. For companies with petabyte archives the figure reaches six digits, and it has worked as an exit tax.
The EU Data Act, Regulation (EU) 2023/2854, tackles this in Chapter VI. Article 29 set a three-year glide path. From 11 January 2024, vendors of data processing services could charge only reduced switching charges, capped at costs directly linked to the switch. From 12 January 2027, they may impose no switching charges at all, and the definition in Article 2(36) expressly includes data egress charges.
The rule covers infrastructure, platform, and software services sold to customers in the EU, and it applies when a customer moves to a different vendor or back to its own servers.
It does not make all outbound traffic free.
What Customers Misread
The most frequent error is reading “egress fees end” as a blanket rule. The ban covers one flow: data and digital assets extracted to complete a switch. Everyday outbound traffic, such as serving video to users or API responses to customers, remains billable at normal rates.
Multi-cloud use sits in between. Where a customer runs two vendors side by side and moves data between them continuously, Article 34 limits egress charges to the vendor’s own costs. That cap has no end date and does not fall to zero in 2027. The Commission’s published questions and answers say the same.
A third misreading concerns contracts. Standard service fees stay payable through the notice period, and early termination penalties on fixed-term commitments are not switching charges under the Act. A firm with two years left on a committed-spend agreement can leave without transfer fees and still owe the shortfall, which, frankly, dwarfs egress for most mid-sized buyers.
The switching right depends on more than price. Article 25 requires contracts to state a notice period of no more than two months, a transition period of 30 calendar days, and a data retrieval window of at least 30 days afterwards. Article 30 obliges infrastructure vendors to help the customer reach functional equivalence at the destination, and requires platform and software vendors to offer open interfaces and export in a structured, machine-readable format. Custom-built services and test versions are partly exempt under Article 31.
Planning A Cloud Exit
Read The Contract Against Article 25
Pull the current agreement and check five items: notice period, transition period, retrieval window, the list of data and asset categories that can be exported, and any stated switching charges. Contracts signed or renewed since 12 September 2025 should already carry these terms. Older ones may not. Ask the vendor in writing for its Data Act addendum. AWS, Microsoft, and Google each publish one, and their conditions differ on how to give notice and how credits are applied.
Time The Move Around The Date
Before 12 January 2027, at-cost charges are still lawful. After it, the transfer portion of a switch costs nothing. For a 50-terabyte estate the saving is a few thousand dollars at most, so delaying a business-driven migration by months to catch the date seldom pays. For archives of several hundred terabytes it can. France moved early and set these transfer fees at zero from 1 December 2025 under national law.
Budget What The Law Leaves
Transfer fees are the small line. Engineering time to rebuild networking, identity, monitoring, and managed database setups usually runs to weeks or months of staff effort. Add parallel running costs while both environments are live, licence changes, retraining, and any committed-spend shortfall. A plain spreadsheet with those rows gives a truer exit cost than the egress calculator. You list the workloads, price the rebuild, and the transfer fee turns out to be a footnote.
Use The Transition Period Properly
The 30-day transition starts after the notice period ends. If the vendor says 30 days is technically unfeasible, it must tell you within 14 working days of the request, give reasons, and propose an alternative of no more than seven months. Customers may also ask for an extension once. During transition the old vendor must keep the service running and maintain security. After the retrieval window, it must erase your exportable data. Get that erasure confirmed in writing.
Two Switching Scenarios
A 30-person software company. The firm holds 50 terabytes in object storage and runs a dozen virtual machines with a US hyperscaler on pay-as-you-go terms. It plans to move to a European host in February 2027. It gives two months’ notice in mid-December, transfers data during the 30-day transition, and pays no transfer charge under Article 29. The avoided fee is about $4,300. The migration itself consumes roughly six engineer-weeks, mostly rewriting deployment scripts and replacing a managed queue service that has no direct equivalent at the new host. The legal change removed an irritant. The effort stayed.
A media analytics firm. The company keeps its footage archive with one vendor and sends about 2 terabytes a night to another vendor’s data warehouse for analysis. This is in-parallel use, not a switch. After January 2027 its nightly transfer remains chargeable, capped at the sending vendor’s costs. It asks for the at-cost rate and receives a discount against list, not a zero. Its finance lead had budgeted for free transfer on the strength of a headline. A correction followed in the next forecast.
What Stays Chargeable
| Cost Item | Until 11 January 2027 | From 12 January 2027 | Basis |
|---|---|---|---|
| Egress for a switch | Reduced, capped at direct cost | Prohibited | Article 29 |
| Other switching charges | Reduced, capped at direct cost | Prohibited | Articles 2(36) and 29 |
| Egress for in-parallel use | Chargeable at cost | Still chargeable at cost | Article 34 |
| Everyday outbound traffic | Normal rates | Normal rates | Outside the switching rules |
| Service fees during notice | Payable | Payable | Excluded from switching charges |
| Early termination penalty | Payable if agreed and disclosed | Payable if agreed and disclosed | Contract law, Article 25 transparency |
| Migration engineering | Customer’s cost | Customer’s cost | Not regulated |
Common Mistakes
Treating voluntary programmes and legal rights as the same thing. Since early 2024 the three largest vendors have offered free data transfer for customers who leave, usually on application and with conditions such as closing the account within a set period. The Data Act right needs no application, but its notice and transition steps still apply.
Assuming the rule covers customers anywhere. It protects customers in the EU. A UK or US entity relies on its vendor’s own policies or local competition remedies, and it rarely matches the EU terms line for line.
Forgetting software services. A customer relationship or accounting platform is a data processing service too. Its vendor must export your data in a usable format and may not charge for the switch after the date.
Relying on pending amendments. The Commission’s Digital Omnibus proposal of 19 November 2025 would ease some switching duties for custom-made services and smaller vendors on older contracts. It leaves Article 29 untouched, and it is a proposal, not law.
Skipping a test export. Discovering during the 30-day window that a database dump takes nine days to produce is avoidable. Run a partial export a quarter earlier.
FAQ
Are cloud egress fees banned in the EU from 2027?
For switching vendors or moving on-premises, yes, from 12 January 2027. Routine outbound traffic and multi-cloud transfers are not covered by the zero-fee rule.
Does the Data Act cancel my fixed-term cloud contract?
No. You can switch, but agreed early termination penalties and unused commitments remain payable. Contracts must disclose them.
How long does a cloud vendor have to complete a switch?
After a notice period of up to two months, the transition period is 30 calendar days, extendable to at most seven months where the vendor shows technical unfeasibility.
Is multi-cloud data transfer free under the Data Act?
No. Egress for parallel use of two vendors may be charged, but only up to the costs the vendor incurs.
Does the rule apply to SaaS products?
Yes. Software, platform, and infrastructure services all count as data processing services, with partial exemptions for custom-built and test versions.
Author’s Insight
Reading Chapter VI alongside the Commission’s guidance and the hyperscalers’ addenda, the fee ban is the most visible part of the switching rules and probably the least consequential. Transfer charges were a deterrent mainly at very large data volumes. For typical estates, proprietary managed services and committed-spend contracts hold customers far more firmly, and the Act addresses those only through transparency and interface duties. The UK competition authority’s October 2026 update noted limited uptake of free-switching schemes, which fits that reading. The practical gain for buyers is a stronger negotiating position at renewal, since a credible exit now has a defined timetable and one fewer cost.
What to Remember
- From 12 January 2027, cloud and software vendors may not charge EU customers for the switching process, data egress included.
- Until then, switching charges are lawful only up to the vendor’s direct costs.
- Multi-cloud transfers stay chargeable at cost, and ordinary outbound traffic stays at normal rates.
- Contracts must set a notice period of at most two months, a 30-day transition, and a 30-day retrieval window.
- Early termination penalties and migration engineering remain the customer’s burden and usually exceed transfer fees.
- Check your vendor’s Data Act terms, run a test export, and watch the Digital Omnibus for changes. This article is general education, not legal advice.